March Brings EYW Passenger Count To New Heights


  • April 16, 2024
  • /   Katie Atkins
  • /   Concourse A
Airplanes lined up at aiport gates
The new concourse's steel roof structure as of Tuesday, April 16, 2024, can be seen beyond a lineup of aircraft responsible for bringing an increase of 15 percent more passengers to EYW in the first quarter.

EYW Maintains Stellar Credit Rating


  • February 1, 2024
  • /   
  • /   Concourse A
A photo of eye glasses next to a credit score information sheet.
Fitch Ratings: Airport Financial Outlook Stable

Record-Breaking December Numbers At EYW; Airline Capacity To Increase 20.8 Percent In Q1


  • January 19, 2024
  • /   
  • /   Concourse A
Construction workers are pictured with a bulldozer.
Concourse A’s ongoing construction by NV2A Gulf Keystar JV’s subcontractors Toppino (civil work), Bella (concrete structure), and Florida Keys Electric (electrical work).

Concourse A Update #19


  • October 11, 2023
  • /   
  • /   Concourse A
A photo of an active construction site with machinery and workers in hard hats.
Two out of three concrete pours are complete.

Concourse A Update #18


  • September 1, 2023
  • /   
  • /   Concourse A
Construction preparation for elevated concrete deck.
Formwork installation continues.

Concourse A Update #17


  • July 28, 2023
  • /   
  • /   Concourse A
A photo of construction in progress, including preparation for concrete, at Key West International Airport.
Crews are preparing for tie beam and precast joint installation.

Concourse A Update #15


  • June 30, 2023
  • /   
  • /   Concourse A
Passengers boarding plane outside of construction zone.
Passengers board an American Airlines flight on Monday, June 26, 2023, amid ongoing construction.

Concourse A Update #14


  • June 20, 2023
  • /   
  • /   Concourse A
Construction site showing concrete columns.
This photo shows the construction site on June 19, 2023.

Concourse A Update #13


  • June 2, 2023
  • /   
  • /   Concourse A
Construction in progress.
A second live camera feed has been added facing the east side of the construction zone.

Concourse A Update #12


  • May 19, 2023
  • /   
  • /   Concourse A
Vertical columns.
Vertical columns continue to be poured.